| |
|
 |
| The Link Centre is a large leisure complex, comprising of an international-sized ice skating rink, swimming pool, indoor courts, climbing walls, a fitness studio and the local library. |
 |
| Voltage optimisation was installed as one of a number of energy efficiency measures across the site. |
 |
|
|
 |
| The Link Centre is a large leisure complex, comprising of an international-sized ice skating rink, swimming pool, indoor courts, climbing walls, a fitness studio and the local library. |
 |
| Voltage optimisation was installed as one of a number of energy efficiency measures across the site. |
 |
|
|
 |
|
| |
 |
| All preparations for installation were carried out beforehand, with the final connections made during a four-hour period on a Sunday evening to ensure minimum disruption. |
 |
| Figure 1: Additional plinth supplied to reduce flood risk |
 |
 |
|
|
|
 |
| The regulator outputs were set to 221V (P-N) as the optimised setting, giving just in excess of 220V (P-N) at the furthest point on site as requested by the Client. |
 |
| The initial survey projected a minimum saving of 14% of the overall consumption. The Client required us to prove these savings as confirmation of their own long term tests. It was decided to utilise the Regulator’s ability to adjust phase voltages whilst on-line and load. Medium and short term tests were be performed, in each case returning the site voltages back to near maximum and then reducing again to the optimised setting. Results from these tests combined with other test data allowed the actual savings to be calculated. The site voltages were increased to the maximum and allowed to run for a period. Then reduced to the optimised setting of 221V (P-N) within less than a minute and allowed to run for the same time period. The step change in voltage (all three phase voltages are summed and averaged for clarity) and the consumption are clearly visible (detailed graphs available on request). The results were analysed and comparisons made with the short-term tests. |
 |
| Again, the site voltages were increased to maximum and allowed to run for a short period and then returned to the optimised value, this sequence was repeated on several occasions in short succession. The step changes in voltage (again all three phase voltages are summed and averaged for clarity) and consumption can be clearly defined. Analysed together with the previous results from the medium term test and other data, the calculated savings for this site will be approximately 15% of the usage, an increase over the previous estimate. |
| |
|
|